Cloud over Tamil Nadu government formation as Governor asks Vijay to prove majority | 1 Year of Operation Sindoor: PM Modi says it showed India’s firm response to terror | ‘Larger conspiracy ahead of PM Modi’s visit’: BJP on killing of Suvendu Adhikari’s aide | ‘My car was on OLX for sale’: Siliguri owner says number plate used in Suvendu aide assassination may have been cloned online | ‘Pre-planned political assassination’: BJP’s Swapan Dasgupta on Suvendu aide’s killing | BJP leader Suvendu Adhikari's personal secretary shot dead in West Bengal's Madhyamgram | Mamata Banerjee to move Supreme Court against Bengal post-poll violence, refuses to quit | Who after Mamata in Bengal? Amit Shah to meet BJP MLA-elects ahead of May 9 oath | Vijay’s TVK seeks Congress, Left support after falling short of majority in Tamil Nadu | Jolt to TMC! Supreme Court rejects plea challenging central staff deployment at Bengal counting centres

Centre is all set to start stalled works of 2000 MW Subansiri Lower Hydro project

| | Feb 13, 2017, at 09:35 pm
Guwahati, Feb 13 (IBNS): The Centre is all set to start the construction works of the stalled 2000 MW Subansiri Lower Hydro Electric Project.

A top official of the Union Power Ministry said that, the Centre is targeting to complete the works of the project by mid of 2018.

Arunachal Pradesh Chief Minister Pema Khandu on Sunday said the the Arunachal Pradesh government will sort out all the problems on implementation of the stalled hydro electric project soon.

Khandu said that, he would hold talks with the Centre and his Assam counterpart Sarbananda Sonowal into the matter for an early sorting out the issue.

Khandu and his cabinet colleagues had inspected the construction site of the hydro electric project and assured to the National Hydroelectric Power Corporation (NHPC) officials to sort out the problems for halted construction works soon.

Khandu said that, the state government losing around Rs 1.20 crore per day, which could have been accured from the 12% free power share.

Meanwhile, the top official of the Union Power Ministry said that, the stalled works of the hydro electric project will be started soon.

The construction work of the hydro electric project has been stalled since December 2011 following amid protests by anti-dam groups from Assam including Krishak Mukti Sangram Samittee (KMSS), All Assam Students Union (AASU), Asom Jatiyatabadi Yuba Chatra Parishad (AJYCP).

The anti-dam groups alleged that, the people residing in the downstream will be affected, if is any breach in the project.

The initial cost of the project was estimated at Rs 6285 crore when construction begun in 2005, and now the revised cost estimate has escalated to Rs 17,435 crore, due to delay.

On the other hand, the NHPC official said that, around 55% construction works have been completed till date.


(Reporting by Hemanta Kumar Nath)

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm