Ajit Doval breaks silence on Operation Sindoor in Discovery’s explosive new docuseries | Rahul Gandhi's 'mock hug' taunt sparks row; Centre stresses 'mutual respect' with Italy | Delhi on high alert: Bomb threat to High Court, airport and multiple locations ahead of I-Day | ‘Who are they to interfere?’: CJI Surya Kant slams Bar Council of India over NALSAR students’ enrolment row | 'Shows how low Congress has sunk': BJP slams Rahul Gandhi over Modi foreign policy jibe | From guns to glamour: Former women Maoists walk the ramp in Chhattisgarh | Netaji row: Suvendu Adhikari govt strips BJP MP Anant Maharaj of state honour | Sukhbir Badal attacked by Nihang Sikh with kirpan at Maharashtra gurdwara; assailant detained | ‘If you cannot do it, we will pass an order’: Supreme Court’s final warning to Centre on food labels | ‘Time to move on’: Bombay HC sends strong message in Vijay Mallya-bank dispute

L&T bags EPC orders in Bangladesh

| | May 28, 2014, at 07:25 pm
Mumbai, May 28 (IBNS): Multinational conglomerate Larsen & Toubro (L&T) on Wednesday said it has received two EPC (engineering, procurement and construction) orders valued at around USD 480 million, for setting up dual fuel-fired gas based combined cycle power plants in Bangladesh.
L&T noted that one order of approximately USD 280 million has been received from Marubeni Corporation, Japan, for setting up a 360 MW Bheramara Combined Cycle Power Plant Development Project of North West Power Generation Company Ltd (NWPGCL) in Bangladesh. 
 
NWPGCL, a fully-owned enterprise of the Bangladesh Power Development Board, is currently developing around 750 MW of gas-based power plants in the north-western region of Bangladesh and have awarded the contract to set up the 360 MW Bheramara project in Khulna Division of Bangladesh to Marubeni Corporation, which has in turn awarded the EPC job to L&T on turnkey basis.
 
The order was bagged by L&T against stiff global competition from Japanese and European EPC companies. 
 
The plant will incorporate state-of-the-art advanced class gas turbines and high efficiency steam turbines from Mitsubishi Hitachi Power Systems of Japan, which will be procured by L&T.
 
Another order of approximately USD 200 million has been received from the Bangladesh Power Development Board for setting up a 225 MW Sikalbaha Combined Cycle Power Plant near the port city of Chittagong in Bangladesh.
 
It was bagged against international competition from European, Chinese and Korean EPC companies. 
 
The plant will incorporate state-of-the-art gas turbines and steam turbines from Siemens AG, Germany and other steam turbine manufacturers, which will be procured by L&T.
 
L&T’s scope includes design, detailed engineering, supply, installation and commissioning of the complete power plants on a turnkey basis. 
 
L&T-Sargent and Lundy, a subsidiary of L&T, will carry out the plant integration and detailed engineering, using propriety technology of Sargent & Lundy LLC, USA.
 
According to the officials, L&T has executed several large gas-based power projects on EPC basis in the past for government utilities and independent power producers in India and abroad, and has recently commissioned a 375 MW Gas Based Combined Cycle Power Plant with a Single Shaft advanced class Siemens gas turbine and steam turbine for the Gujarat State Electricity Generation Corporation at Dhuvaran.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.