BJP reshuffles top organisation seven months after Nitin Nabin's elevation | West Bengal STF arrests suspected aide of ISI 'agent' Rana Rauf in Kolkata | ‘Very hopeful’: Indian envoy Dinesh Trivedi breaks silence on PM Tarique Rahman’s proposed India visit | Shehzad Poonawalla doubles down on BJP exit, urges party to accept resignation | Tarapith tragedy: Seven pilgrims killed as hotel goes up in flames before dawn | Bengal STF nabs suspected aide of ISI 'agent' Rana Rauf in Kolkata | After SC rebuke, BCI chief apologises to NALSAR students over enrolment freeze row | Independence Day: PM Modi’s big youth pitch— AI training, free coaching amid exam row and job concerns | ‘Shakti Ki Saptadhara’: Modi reveals 7 pillars to power India’s next leap in his I-Day speech from Red Fort | West Bengal STF arrests 3 more suspected Pakistani spies in Cooch Behar
NTPC

NTPC’s oldest unit at Singrauli records highest PLF so far in current fiscal

| @indiablooms | Jan 11, 2021, at 10:33 pm

New Delhi: NTPC Ltd’s very first unit, which was commissioned 38 years ago at Singrauli in Uttar Pradesh, has achieved the highest Plant Load Factor (PLF) of 100.24 percent among all thermal units in the country between April 2020 to December 2020, data published by Central Electricity Authority (CEA) showed.

The 200 MW unit was commissioned in 1982 and the robust PLF signifies the exceptional operational and maintenance efficiency at India’s largest power generation company.

Besides the exceptional feat achieved by unit#1, three more NTPC units - Singrauli unit#4 and Korba unit #1 & #2 in Chhattisgarh, have figured among Top 5 performing units.

Further, NTPC Group achieved highest gross generation of 222.4 Billion Unit (BU) from April to December 2020, an increase of 3.8 percent compared to the same period last year. Concurrently, NTPC coal power stations have maintained high availability of 92.21 percent from April 2020 to December 2020 as against 87.64 percent during the same period last year.

Six flagship power plants of NTPC i.e. NTPC Korba (2600 MW) & NTPC Sipat (2980 MW) in Chhattisgarh, NTPC Rihand (3000 MW) in Uttar Pradesh, NTPC Vindhyachal (4760 MW) in Madhya Pradesh, NTPC Talcher Thermal (460 MW) and NTPC Talcher Kaniha (3000 MW) in Odisha have also featured among the top 10 performing thermal plants in the country.

With a total installed capacity of 62.9 GW, NTPC Group has 71 Power stations comprising of 24 Coal, 7 combined cycle Gas/Liquid Fuel, 1 Hydro, 14 Renewables along with 25 Subsidiary & JV Power Stations. The group has over 20 GW of capacity under construction, including 5 GW of renewable/hydro energy projects.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.