August 17, 2026 02:29 pm (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
After SC rebuke, BCI chief apologises to NALSAR students over enrolment freeze row | Independence Day: PM Modi’s big youth pitch— AI training, free coaching amid exam row and job concerns | ‘Shakti Ki Saptadhara’: Modi reveals 7 pillars to power India’s next leap in his I-Day speech from Red Fort | West Bengal STF arrests 3 more suspected Pakistani spies in Cooch Behar | Bengal man arrested in Bengaluru over terror links, Afghanistan travel plan | Ajit Doval breaks silence on Operation Sindoor in Discovery’s explosive new docuseries | Rahul Gandhi's 'mock hug' taunt sparks row; Centre stresses 'mutual respect' with Italy | Delhi on high alert: Bomb threat to High Court, airport and multiple locations ahead of I-Day | ‘Who are they to interfere?’: CJI Surya Kant slams Bar Council of India over NALSAR students’ enrolment row | 'Shows how low Congress has sunk': BJP slams Rahul Gandhi over Modi foreign policy jibe
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.