Tragedy in the skies: Five IAF personnel killed in AN-32 crash in Assam | 'Ask probe officers whether I hid anything': Abhishek Banerjee hits back after pre-dawn police search | Police storm Abhishek Banerjee's house at 3 am tracking aide, Mamata arrives; seizure list says 'NIL' | Big boost for India's security: DRDO successfully tests advanced missile shield | Indian-origin man jailed for 34 years in UK over horrific kidnap, torture and rape case | Mamata's nightmare deepens! Saayoni Ghosh, Dev, Rachana Banerjee among 19 rebel MPs seeking TMC split | Trump claims US 'ended war with Iran', Tehran yet to confirm a deal | Heartbreak for Indian sports: Manu Bhaker's mentor Jaspal Rana passes away at 49 | Three Indian seafarers, missing after US strike on tanker near Oman, confirmed dead | 'Choose your side': TMC MP Kalyan Banerjee's ultimatum to Mamata in open revolt against Abhishek
Grid Stations

J&K administration likely to commission two more grid stations in coming months

| @indiablooms | Nov 03, 2021, at 12:18 am

Srinagar/IBNS: The J&K government is likely to commission two more grid stations in Kashmir to augment the power supply capacity from the current 1,650 to 1,850 megawatts (MW) in the next two months. 

With the onset of winter, the peak demand for power in Kashmir has gone up to 1,450 MW from 1,200 MW.

Sources said the “unregulated” use of heating gadgets with the arrival of cold leads to an abrupt rise in energy demand.

“However, the system constraints allowed the Kashmir Power Development Corporation Limited (KPDCL) to supply 1,650 MW at a time,” they said.

Chief Engineer, KPDCL, Aijaz Ahmad Dar, said: “In the coming days with commissioning of two more grid stations at Lassipora and augmentation of the Mir Bazar grid station, we would be able to supply 1,850 MW; currently our distribution capacity is 1,650 MW.”

When asked about the department’s preparedness for winter, he said they have more or less completed all preparations.

“Our buffer poles, transformers stand in place, majority of the preventive maintenance of transmission lines have been completed, and branching cutting will be completed in a few days,” he said.

Last year, due to the commissioning of Alasteng and Bandipora grids, the supply increased up to 327 lakh units per day.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.