CBI moves Supreme Court challenging Kuldeep Sengar's relief in Unnao rape case | Music under attack: Islamist mob attacks James concert with bricks, stones in Bangladesh, dozens hurt | Christmas vandalism sparks mass arrests in Raipur; Assam acts too with crackdown on 'religious intolerance' | BJP's VV Rajesh becomes Thiruvananthapuram Mayor after party topples Left's 45-year-rule in city corporation | ‘I can’t bear the pain’: Indian-origin father of three dies after 8-hour hospital wait in Canada hospital | Janhvi Kapoor, Kajal Aggarwal, Jaya Prada slam brutal lynching in Bangladesh, call out ‘selective outrage’ | Tarique Rahman returns to Bangladesh after 17 years | Shocking killing inside AMU campus: teacher shot dead during evening walk | Horror on Karnataka highway: sleeper bus bursts into flames after truck crash, 9 killed | PM Modi attends Christmas service at Delhi church, sends message of love and compassion
Kashmir schemes

Kashmir: MD KPDCL reviews work progress under Capex Budget, centrally sponsored schemes

| @indiablooms | Jun 03, 2021, at 09:41 pm

The Managing Director, KPDCL, Dr Basharat Qayoom, today chaired a review meeting in the Conference Hall of KPDCL and took a detailed review of Projects under various Central Sponsored Schemes viz R-APDRP, IPDS, PMDP, DDUGJY in Kashmir Valley.

The MD was briefed by respective PIAs about Scheme Wise progress made till date and informed likely completion of various Works/projects under different schemes. The Managing Director was informed that twenty out of seventy R/Stns have been completed till date and ten R/Stns are likely to be completed in the month of July 2021.

The Managing Director, KPDCL, gave strict directions to the executing agency for adherence to the timelines for completions of various projects under different schemes.

The issues regarding hampering of work at new 10MVA R/Stn at Ranger, Chadoora& augmentation of SafaKadal R/Stn from 6.3MVA to 10MVA under PMDP-Urban were also discussed in the meeting and MD KPDCL stressed on making efforts to resolve the same on fast track basis. The MD KPDCL also directed the concern to complete the work of Hachaipora 6.3MVA R/Stn under DDUGJY on priority.

Also, the issue of additional funds for 33KV Bandipora –Gurez line was decided to be put forth before next BoD meeting. The chair further laid stress on works under DDUGJY and GIS Substations under IPDS and informed all the executing agencies that no further extension will be granted from the Ministry of Power, Govt of India, and as such physical and financial component of works be completed by or before the deadline fixed by
Ministry of Power, GoI.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.