G7 declares war on global drug cartels, unveils major anti-trafficking plan | India, Canada launch security pact talks, target trade deal completion in 2026 | PM Modi flags seafarer safety at G7, calls for secure maritime routes amid Hormuz tensions | Messi makes history with first World Cup hat-trick, equals Klose's all-time record in Argentina's 3-0 win | Tragedy in the skies: Five IAF personnel killed in AN-32 crash in Assam | 'Ask probe officers whether I hid anything': Abhishek Banerjee hits back after pre-dawn police search | Police storm Abhishek Banerjee's house at 3 am tracking aide, Mamata arrives; seizure list says 'NIL' | Big boost for India's security: DRDO successfully tests advanced missile shield | Indian-origin man jailed for 34 years in UK over horrific kidnap, torture and rape case | Mamata's nightmare deepens! Saayoni Ghosh, Dev, Rachana Banerjee among 19 rebel MPs seeking TMC split
Jhelum River

Kashmir's Jhelum river carrying capacity enhanced by 25 percent from 2014

| @indiablooms | Oct 13, 2021, at 10:48 pm

Srinagar/IBNS: To prevent 2014-like floods in the Kashmir division, the carrying capacity of the river Jhelum has been enhanced by 25 percent by dredging of the river and its flood spill channels.

The 2014 devastating floods in Srinagar and its adjoining areas wreaked havoc and caused an estimated one lakh crore loss to the public and private infrastructure.

Subsequently, the Centre announced a 'Plan for Comprehensive flood management of River Jhelum and its tributaries’.

The Flood Management Plan was divided into two parts- Phase 1 and Phase 2- and so far 98 percent progress has been achieved on phase 1, while for phase 2 the J&K administration is awaiting release for funds from the Centre.

Chief Engineer of Irrigation and Flood Control Naresh Kumar said, "Carrying capacity of river Jhelum has been enhanced by 25 percent from what it was in 2014. We have done spot dredging of flood channels where the need was felt to do so.

He said, "For Phase 2 part A, investment clearance for Rs 1,623 crore has been already cleared, now we are awaiting release of funds as the Department of Water Resources have informed that funds will be released only  after they will put this project in their five year plan for 2022-26."

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.