Bangladesh poll manifestos mirror India’s welfare schemes as BNP, Jamaat bet big on women, freebies | Drama ends: Pakistan makes U-turn on India boycott, to play T20 World Cup clash as per schedule | ‘Won’t allow any impediment in SIR’: Supreme Court pulls up Mamata govt over delay in sharing officers’ details | India-US trade deal: ‘Negotiations always two-way’, says Amul MD amid farmers’ concerns | Khamenei breaks 37-year-old ritual for first time amid escalating Iran-US tensions | India must push for energy independence amid global uncertainty: Vedanta chairman Anil Agarwal | Kanpur horror: Lamborghini driven by businessman’s son rams vehicles, injures six | ‘Namaste Trump beat Howdy Modi’: Congress slams PM Over India-US trade deal | Historic India-US trade pact: Tariffs cut, $500B market opportunity unlocked! | Big call from RBI: Repo rate stays at 5.25%, neutral stance continues
Tunnel collapse
Image of rescue ops tweeted by Uttarkashi Police

Rescue work in Uttarakhand tunnel collapse put on hold after loud 'cracking sound' was heard

| @indiablooms | Nov 18, 2023, at 05:43 am

The Uttarakhand tunnel rescue work hit another roadblock Friday as the drilling operations were put on hold after 2:45 pm following a large cracking sound. A meeting of experts has been called.

The 40 workers have been trapped inside the 4.5-km Silkyara tunnel since Sunday morning when a part of the under-construction structure near Uttarkashi collapsed following a landslide.

"During the execution of the work at around 2:45 pm, a large scale cracking sound was heard by officials and the team working inside the tunnel and created a panic situation in the tunnel as well as to the team working," the National Highways & Infrastructure Development Corporation Limited (NHIDCL) said in a statement.

It said there's a "strong possibility that a further collapse may take place and accordingly pipe pushing activity has been stopped".

The rescuers need to drill up to 60 metres to insert 800 mm and 900 mm diameter pipes with the help of a giant drill machine to create an escape passage for the stranded workers.

"Positioning of the fifth pipe was under progress. It was reported that the machine was not able to push further as it was getting lifted and the bearings of the machine were damaged.  It was planned to fix the machine by anchors to avoid uplifting. It was decided and agreed by the special agency executing the work that further pushing of the pipe will be feasible only if the machine is placed with the same inclination as the pipe," the statement said.

Elite rescue teams from Thailand and Norway, including the one that successfully rescued the trapped children from a cave in Thailand in 2018, have joined the rescuers to aid in the ongoing rescue operation.

The round-the-clock rescue work is being helmed by 165 personnel from multiple agencies, including NDRF, SDRF, BRO, and the ITBP.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.