Kolkata: Taratala warehouse roof collapses | Indian Army's Trishakti Corps restores lifeline connectivity in North Bengal between Siliguri and Mirik | 19 million barrels flow through Strait of Hormuz, Trump declares oil prices are falling | No Hindi, no NEET: Vijay reignites Tamil Nadu's biggest political flashpoints | Messi creates World Cup history with record-breaking double; Mbappe equals Klose's mark hours later | Tech giant Oracle slashes 21,000 jobs while betting big on AI | 'Italy and I never beg': Meloni fires back at Trump over G7 photo claim | No more 'brother': Stalin's formal birthday greeting to Rahul reflects deepening rift | TMC seeks disqualification of 20 rebel MPs, Abhishek says 'membership should go' | Nara Lokesh pitches Andhra Pradesh as investment hub during Kolkata visit, sets $2.4 trillion economy goal
Dasu Project
Image: Twitter

Pakistan: Dasu Hydropower Project to miss completion deadline

| @indiablooms | Jan 07, 2023, at 03:37 am

Islamabad: The construction of the Dasu Hydropower Project (Stage-I), which has an installed capacity of 2,160 MW, will now miss the earlier competition deadline.

Power generation from the project is now expected to take place from 2026 end.

Project management, while giving a briefing to WAPDA Chairman Lt-Gen (Retd) Sajjad Ghani during his visit to Dasu Hydropower Project, said construction work was continuing simultaneously on 12 different sites, reports The Nation.

The critical diversion system will be completed in May 2023, while electricity generation from the project will commence by the end of 2026, said a statement issued here by WAPDA.

Due to Land acquisition issues, the COVID Pandemic, and terrorism incidents which are all beyond the control of Wapda, the expected COD of the Dasu Stage-I Hydropower Project (HPP) has been pushed till FY 2026-27, said WAPDA in its bulk supply tariff petition shared with National Electric Power Regulatory Authority (NEPRA), reports The Nation.

WAPDA had requested NEPRA to allow an extension in COD of the project till 2026-27.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.