Tragedy in the skies: Five IAF personnel killed in AN-32 crash in Assam | 'Ask probe officers whether I hid anything': Abhishek Banerjee hits back after pre-dawn police search | Police storm Abhishek Banerjee's house at 3 am tracking aide, Mamata arrives; seizure list says 'NIL' | Big boost for India's security: DRDO successfully tests advanced missile shield | Indian-origin man jailed for 34 years in UK over horrific kidnap, torture and rape case | Mamata's nightmare deepens! Saayoni Ghosh, Dev, Rachana Banerjee among 19 rebel MPs seeking TMC split | Trump claims US 'ended war with Iran', Tehran yet to confirm a deal | Heartbreak for Indian sports: Manu Bhaker's mentor Jaspal Rana passes away at 49 | Three Indian seafarers, missing after US strike on tanker near Oman, confirmed dead | 'Choose your side': TMC MP Kalyan Banerjee's ultimatum to Mamata in open revolt against Abhishek

Minister updates Lok Sabha about Delhi-Jaipur Expressway

| | Mar 03, 2016, at 09:09 pm
New Delhi, Mar 3 (IBNS) In a written reply to the Lok Sabha on Thursday, Minister of State for Road Transport & Highways, Pon Radhakrishnan, said that out of the 93 structures proposed for the six laning of Delhi- Jaipur Project, nine structures have been deleted and 17 structures have been de-linked due to non availability of land.
Construction of the 17 de-linked structures envisaged in the project for smooth flow of traffic depends upon availability of encumbrance free land. 
 
Total 93 structures (flyovers and underpasses) had been proposed on six laning of Delhi- Jaipur Project, which is on BOT mode. 
 
The minister also informed that of the remaining 67 structures, 61 have been completed and five structures are expected to be completed by June 2016. 
 
One flyover (at Hero Honda Chowk) is targeted to be completed by May 2017. A budgetary provision of Rs. 53.90 crore has been kept during the financial year 2015-16 for construction of this flyover on EPC mode. After construction of flyover at Hero Honda Chowk, congestion on the project highway is likely to be decreased. 
 
Regarding the Delhi-Jaipur Expressway, feasibility study is in progress, he said.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.